Data centers are turning to old jet engines as the wait for power grows
The years-long wait for access to the grid and new turbines is causing data center builders to turn to an unusual, less efficient and less environmentally friendly solution: once-discarded jet engines.
Aditya Mehta
2:19 PM PST · November 3, 2026
Stuck in years-long lines for grid connections and new turbines, some AI data centers are making their own electricity with converted jet engines, the New York Times reported Tuesday.
The engines, pulled from retired aircraft and rebuilt to burn natural gas, aren’t anyone’s idea of a permanent power plant. But they’re another sign of how far power supply has fallen behind the AI buildout.
For companies stuck in those lines, the main draw of converted jet engines is how quickly the engines can be up and running. “It’s all about getting power as fast as possible,” Rystad Energy analyst Audun Martinsen told the Times. With jet-powered units, “they can have a data center running in 24 months,” he said.
Hooking up 100 megawatts to the grid in Northern Virginia, by comparison, takes about seven years , according to the International Energy Agency. Most power capacity is expected to come on by 2031, an executive at Mitsubishi Power, one of the world’s top makers of power generation equipment told Bloomberg last week.
In some cases, these delays are already costing some data center operators business. Last month, Microsoft pulled out as the anchor customer for Nscale’s data center in Loughton, England, after the local utility said it couldn’t deliver enough power until the early-to-mid 2030s.
Elon Musk’s xAI is among the companies already using the engines, having installed eight converted jet-engine turbines in Mississippi to help power its Colossus 2 data center in Memphis, the Times reported, citing state permits and satellite imagery. The units come from ProEnergy, which rebuilds a GE engine commonly found on Boeing jets.
In 2025, OpenAI followed Musk’s lead with gas turbines at its first Stargate site in Abilene, Texas. Crusoe, a Denver-based startup that builds AI data centers, is constructing that Abilene campus and ordered 13 of ProEnergy’s converted units in April.
In September, Crusoe walked away from a $1.25 billion deal to buy 29 natural gas turbines from Boom Supersonic, a startup developing a supersonic passenger jet that has also begun selling a version of that jet’s engine as a power plant for data centers. A Crusoe spokesperson told TechCrunch at the time that the company still plans to use turbines.
Currently the Trump administration is adding to the pressure by encouraging data centers to generate their own electricity.
Converted jet engines come with trade-offs, though: They’re less efficient and pollute more than turbines designed for conventional gas plants and it takes more of them to make the same amount of power, according to the Times. That may ultimately make converted jet engines a short-term play with some experts saying that efficiency and environmental concerns may grow in importance in a year or two.
Topics
AI , data centers , TC
When you purchase through links in our articles, we may earn a small commission . This doesn’t affect our editorial independence.
Aditya Mehta
Editorial Fellow
Aditya Mehta is a reporter at TechCrunch covering AI. He’s supported by the Tarbell Center for AI Journalism and attended UC Berkeley. You can contact from Aditya by emailing [email protected] or via encrypted message at adymehta.74 on Signal.
View Bio
November 4
Boston
Buy One Pass, Get a Second Free
Cover more ground at TechCrunch’s ultimate founder bootcamp of the year by bringing your co-founder or partner for free
Book before the BOGO deal expires
Register Now
Most Popular
Anthropic warns that it’s very close to RSI capability, aka self-building AI
Julie Bort
New York Times and other outlets sue web browser Brave over alleged content scraping
Rebecca Bellan
Anthropic expected to receive high ‘junk’ rating from credit agencies following IPO, FT report says
Lucas Ropek
Google’s first data center satellite is online and writing poetry
Tim Fernholz
Binance pauses withdrawals as hackers suspected of stealing billions in crypto
Zack Whittaker
As search traffic dries up, Reddit announces it’s shifting to a logged-in experience
Sarah Perez
AI execs may be too out of touch to build for the general public
Amanda Silberling
Loading the next article
Error loading the next article
本文内容由 ai007 从公开渠道聚合,版权归原作者所有。若原文已删除或变更, 以原文站为准;本站存档仅为便于查阅而保留。